Shut off, cap, or control — and notify
For every service entering the building, one of three things has to happen before demolition: shut it off, cap it, or otherwise control it. And in each case, any utility company involved must be notified in advance (§1926.850(c)). The utility often has to make the disconnection or verify it at their equipment.
- Electric — de-energized and confirmed dead, not just breaker-off.
- Gas — shut off and capped; purge lines that could still hold fuel.
- Water, steam, sewer — isolated so lines don't flood or scald the work area.
- Every affected utility company notified ahead of time.